The Solution
Planning and Project Management
Our migration methodology is designed to focus on minimising downtime, reducing risks and guaranteeing the efficient delivery of server migration projects. A key element of this process is ensuring that your project manager has prepared for the challenges and utilised the available resources in the most effective way. With this is mind, we assigned a dedicated project manager to ensure all key objectives were met to our market leading standards.
The Pre-Cable
Pre-cabling is a key strategy for ensuring that we achieve our goal of minimising downtime. With Cunningham and Lindsey this meant our engineers were pre-cabling the new location 4 weeks ahead of the migration. As part of this process, we installed the copper and fibre cables in line with requirements outlined by our partners CDW. As a result, on the day of the migration, the cables were hung ready to install.
The Migration
On the day of the migration, Technimove engineers arrived onsite 30 minutes prior to the start of the migration to sign in and prepare packaging material.
Once onsite, the devices were handed over to Technimove to systematically Decommission, De-rack and wrap in anti-static bubble wrap for protection, before being placed into purpose built, foam lined, server flight cases.
Once the flight cases were secured in the pre-fuelled GPS tracked Mercedes sprinters, Technimove travelled directly to the destination site via the safest and shortest pre-planned route.
Once at Node 4 Data Centre, the equipment was unpacked and installed in line with the destination rack plans. Once racked, devices were recommissioned in line with the patching schedules. Technimove undertook final checks before handing the equipment back over the client for the testing to commence ahead of schedule.
The Result
In partnership with CDW, we ensured through our project management and pre-migration activities that the project was delivered on time and with no issues.
As a result, we delivered above and beyond expectations by;
- Unloading and packing all 19 servers within 2 hours
- Reduced, restrained, installed and connected devices within 3 hours
- Completing the whole project a full 4 hours ahead of schedule.